Project Description
UCLAN – Chiller Installation
This project for the University of Central Lancashire comprised the replacement of existing roof top chiller plant with two new Daikin cooled air chillers.
Work at high level included crane lift to site the new equipment.
Existing pipework feeding the chilled water was repaklced as part of this work. New chilled water pumps, low loss header and pressurisation unti were also installed in the plant room.
Ceiling mounted fan coil cassette units were installed to various areas with appropriate pipework and electrical connections.
A new controls system was installed by Nyke energy including modifications to the existing panel.
Project Value £290,000
Client University of Central Lancashire
Prinicpal Contractor
Energy Effciency